第2页 CAP 123H BUILDING (REFUSE STORAGE AND MATERIAL RECOVERY CHAMBERS AND REFUSE CHUTES) REGULATIONS

[接上页]

  (1) Every plan relating to a building of a description, or 2 or more buildings both or all of which are of the same description, specified in the first column of the Schedule with a total floor area specified opposite that description of building in the second column thereof shall show provision for a refuse storage and material recovery chamber or material recovery chamber of the description specified opposite that floor area in the third column and such refuse storage and material recovery chamber or material recovery chamber shall have a total floor space of not less than that specified opposite that refuse storage and material recovery chamber or material recovery chamber in the fourth column thereof.
  
  (2) In the case of a plan relating to 2 or more buildings falling within 2 or more of the descriptions specified in the first column of the Schedule, paragraph (1) shall apply as if those buildings were comprised in a single composite building and the plan related to that composite building.
  
  (3) This regulation shall not apply to a building constructed or adapted for use principally as a church, a school or a car park.
  
  (39 of 2000 s. 7)
  
  Cap 123H reg 4 Refuse storage and material recovery chambers to comply with regulations 5 to 12A
  
  Expanded Cross Reference:
  
  5, 6, 7, 8, 9, 10, 11, 12, 12A
  
  Where a refuse storage and material recovery chamber is provided in any building it shall be so designed as to comply with the requirements of regulations 5 to 12A. <* Note - Exp. X-Ref.: Regulations 5, 6, 7, 8, 9, 10, 11, 12, 12A *>
  
  (39 of 2000 s. 7)
  
  Cap 123H reg 4A Material recovery chambers to comply with regulations 5 to 12A
  
  Remarks:
  
  5, 6, 7, 8, 9, 10, 11, 12, 12A
  
  Where a material recovery chamber is provided in any building it shall be so designed as to comply with the requirements of refuse storage and material recovery chambers set out in regulations 5 to 12A. <* Note - Exp. X-Ref.: Regulations 5, 6, 7, 8, 9, 10, 11, 12, 12A *>
  
  (39 of 2000 s. 7)
  
  Cap 123H reg 4B Refuse storage and material recovery rooms to comply with regulations 8(1), 12A, 12B and 12C
  
  Where a refuse storage and material recovery room is provided on any floor in any building it shall be so designed as to comply with-
  
  (a) the requirements of refuse storage and material recovery chambers set out in regulations 8(1) and 12A; and
  
  (b) the requirements of regulations 12B and 12C.
  
  (39 of 2000 s. 7)
  
  Cap 123H reg 5 Access to refuse storage and material recovery chambers for emptying refuse containers and recovered materials
  
  (1) Every refuse storage and material recovery chamber shall be of a design approved by the Building Authority and in such location approved by the Building Authority as to provide ready access thereto for the purpose of removing any refuse container and recovered materials stored in such refuse storage and material recovery chamber.
  
  (2) Where access to any refuse storage and material recovery chamber other than a refuse storage and material recovery chamber with vehicular access is obtained along a passage or alley or similar way, the passage, alley or other way shall be not less than 1.5 m in width, shall be without steps and paved and shall have a longitudinal gradient not greater than 1 in 20.
  
  (39 of 2000 s. 7)
  
  Cap 123H reg 6 Refuse storage and material recovery chambers to be fully enclosed save for door etc.
  
  Save for the access door provided in accordance with regulation 10, the opening for any refuse chute and any opening for a hopper, there shall be no openings in any refuse storage and material recovery chamber.
  
  (39 of 2000 s. 7)
  
  Cap 123H reg 7 Refuse storage and material recovery chambers to have one external wall
  
  Not less than one of the walls of every refuse storage and material recovery chamber shall be an external wall.
  
  (39 of 2000 s. 7)
  
  Cap 123H reg 8 Minimum dimensions of refuse storage and material recovery chambers
  
  (1) No refuse storage and material recovery chamber shall have any dimension less than 1.5 m.
  
  (2) The height, measured to the ceiling, of every refuse storage and material recovery chamber shall, throughout the chamber, be not less than 2 m.
  
  (39 of 2000 s. 7)
  
  Cap 123H reg 9 Construction of refuse storage and material recovery chambers
  
  (1) Every refuse storage and material recovery chamber shall be constructed of brickwork, concrete or other approved material.
  
  (2) The whole of the internal faces of the walls of every refuse storage and material recovery chamber shall be lined with glazed bricks, glazed tiles or other approved material.
  
  (3) The ceiling of every refuse storage and material recovery chamber shall be rendered in cement and finished with a smooth surface.
  
  (4) The floor of every refuse storage and material recovery chamber shall be-
  
  (a) constructed of concrete not less than 100 mm thick; (L.N. 439 of 1990)
  
  (b) laid to fall towards the gully provided in accordance with regulation 11; and
  
  (c) finished with quarry tiles or other approved hard impervious material.(5) In every refuse storage and material recovery chamber the junction of the floor with the walls shall be coved.