(Cap 400 section 27) [17 February 1989] (L.N. 45 of 1989) (L.N. 28 of 1989) Cap 400A reg 1 Citation These regulations may be cited as the Noise Control (General) Regulations. (Enacted 1989) Cap 400A reg 2 Completion of forms under regulations 3 and 4 A form prescribed under regulations 3 and 4 shall be- (a) completed legibly by the person submitting the form; and (b) signed- (i) where the person submitting the form is an individual acting on his own behalf or as a partner on behalf of a partnership, by that individual; or (ii) where the person submitting the form is a body corporate, by an individual authorized in that behalf by that body corporate. (Enacted 1989) Cap 400A reg 3 Application for construction noise permit for construction work other than percussive piling (1) An application under section 8(2) of the Ordinance for a construction noise permit for either or both of the following- (a) the use of powered mechanical equipment for the purpose of carrying out construction work other than percussive piling between the hours of 7 p.m. and 7 a.m., or at any time on a general holiday; (b) the carrying out of prescribed construction work at any place within a designated area between such hours, or at any such time,shall be- (i) in Form 1 in the Schedule; and (ii) submitted to the Authority together with the fee prescribed by regulation 8(1) not earlier than 6 months prior to the date specified in the application for commencement of the construction work unless the Authority agrees to accept submission of the application at an earlier time.(2) In this regulation and the Schedule, "prescribed construction work" (订明建筑工程) means the construction work prescribed by the Noise Control (Construction Work) Regulation (Cap 400 sub. leg.) for the purposes of section 6(2) of the Ordinance. (Enacted 1989. L.N. 28 of 1996) Cap 400A reg 4 Application for construction noise permit for percussive piling An application under section 8(2) of the Ordinance for a construction noise permit for the purpose of carrying out percussive piling between the hours of 7 a.m. and 7 p.m. on any day, not being a general holiday, shall be- (a) in Form 2 in the Schedule; and (b) submitted to the Authority together with the fee prescribed in regulation 8 not earlier than 9 months prior to the date specified in the application for the commencement of the percussive piling unless the Authority agrees to accept submission of the application at an earlier time. (Enacted 1989) Cap 400A reg 5 Form of construction noise permit A construction noise permit issued- (a) in respect of an application referred to in regulation 3, shall be in Form 3 in the Schedule; and (b) in respect of an application referred to in regulation 4, shall be in Form 4 in the Schedule. (Enacted 1989) Cap 400A reg 6 Form of noise abatement notice A noise abatement notice served under section 13(1) of the Ordinance shall be in Form 5 in the Schedule. (Enacted 1989) Cap 400A reg 7 Form of notice cancelling a noise abatement notice or varying any requirement therein A notice served under section 13(4) of the Ordinance- (a) cancelling a noise abatement notice shall be in Form 6 in the Schedule; (b) varying any requirement in a noise abatement notice shall be in Form 7 in the Schedule. (Enacted 1989) Cap 400A reg 7A Form of notice requiring a product to be measured, inspected or tested A notice served under section 16(1) of the Ordinance shall be in Form 8 in the Schedule. (L.N. 425 of 1991) Cap 400A reg 7B Form of notice cancelling a notice requiring a product to be measured, inspected or tested, or varying any requirement therein A notice served under section 16(3) of the Ordinance- (a) cancelling a notice requiring a product to be measured, inspected or tested shall be in Form 9 in the Schedule; (b) varying any requirement in a notice requiring a product to be measured, inspected or tested shall be in Form 10 in the Schedule. (L.N. 425 of 1991) Cap 400A reg 8 Fees payable on application for a construction noise permit (1) The fee payable on application for a construction noise permit referred to in regulation 3 shall be $690. (2) The fee payable on application for a construction noise permit referred to in regulation 4 shall be $635. (Enacted 1989. L.N. 261 of 1994; L.N. 496 of 1996; L.N. 581 of 1997; L.N. 307 of 2000) Cap 400A SCHEDULE [regulations 3, 4, 5, 6, 7, 7A & 7B] (L.N. 425 of 1991) FORM 1 [regulation 3] NOISE CONTROL ORDINANCE (Chapter 400) SECTION 8(2) You will be informed of the result of the application within 28 days GW-CNP APPLICATION FOR A CONSTRUCTION NOISE PERMIT FOR THE USE OF POWERED MECHANICAL EQUIPMENT FOR THE PURPOSE OF CARRYING OUT CONSTRUCTION WORK OTHER THAN PERCUSSIVE PILING AND/OR THE CARRYING OUT OF PRESCRIBED CONSTRUCTION WORK A. DETAILS OF APPLICANT 1. Name (person or company) : .................................................................................. ................................................................................................................................. |