第13页 CAP 59I CONSTRUCTION SITES (SAFETY) REGULATIONS

[接上页]

  (b) if the contractor is a firm, the name under which it carries on business and the name and address of every partner in the firm;
  
  (c) the name and address of every subcontractor employed on the work;
  
  (d) the location of the construction site;
  
  (e) the nature of the work;
  
  (f) the date upon which the work was commenced;
  
  (g) whether any mechanical power is being or will be used in connection with the work and, if so, the nature of the mechanical power; and
  
  (h) the expected duration of the work.(2) Paragraph (1) shall not apply if-
  
  (a) at the date of commencement of the work-
  
  (i) the contractor has reasonable grounds for believing that the work will be completed in a period of less than 6 weeks from that date; or
  
  (ii) any other construction work is being undertaken at the same construction site and the information specified in paragraph (1) has been furnished to the Commissioner in respect of that construction work; or(b) not more than 10 workmen are or will be employed on the work at any one time.(3) For the purpose of this regulation, "subcontractor" (次承建商) means a person employed by a contractor to perform construction work under a contract for services. (L.N. 258 of 2003)
  
  Cap 59I reg 57 Further information
  
  If requested by the Commissioner, by notice in writing, a contractor required to furnish information under regulation 56 shall, within 14 days from the date of the notice, furnish in writing to the Commissioner such further information in respect of the relevant construction work as may be specified in the notice.
  
  Cap 59I reg 58 Notification of change
  
  Whenever a material change occurs in respect of any information furnished to the Commissioner under regulation 56 or 57, the contractor undertaking the relevant construction work shall, within 7 days after becoming aware of it, notify the Commissioner in writing of the change.
  
  Cap 59I reg 59 Notification of completion
  
  A contractor required to furnish information under regulation 56 shall, within 7 days after the date of completion of the relevant construction work, notify the Commissioner in writing of the date of completion.
  
  Cap 59I reg 60 Interpretation
  
  PART IX
  
  HEALTH AND WELFARE
  
  Provision of First Aid Facilities
  
  (1) In this Part, unless the context otherwise requires-
  
  "person trained in first aid" (曾受急救训练的人) means a person who-
  
  (a) holds a current certificate of competency in first aid issued by the St. John Ambulance Association;
  
  (b) is a registered nurse within the meaning of the Nurses Registration Ordinance (Cap 164); or
  
  (c) has otherwise completed a course of training in first aid approved by certificate under the hand of the Commissioner.(2) For the purposes of this Part, the number of persons employed at a construction site shall be taken to be the number of persons actually working there at any one time.
  
  Cap 59I reg 61 Provision of first aid box or cupboard
  
  (1) The contractor responsible for a construction site at which 5 or more workmen are employed shall provide and maintain so as to be readily accessible a separate first aid box or cupboard for every 50 workmen or part thereof employed on the site.
  
  (2) For the purposes of paragraph (1), a first aid box or cupboard shall-
  
  (a) contain the items specified in the Second Schedule and any additional items required under paragraph (3); and
  
  (b) have a sufficient capacity to hold those items.(3) The Commissioner may, by notice in writing to the contractor, require him to provide at the construction site any of the following additional items-
  
  (a) two wooden splints measuring 900 millimetres long, 60 millimetres wide and 10 millimetres deep; (L.N. 238 of 1983)
  
  (b) two wooden splints measuring 600 millimetres long, 60 millimetres wide and 10 millimetres deep. (L.N. 238 of 1983)(4) The contractor shall at all times ensure that-
  
  (a) the items in the box or cupboard are maintained in a serviceable and sanitary condition; and
  
  (b) all materials for dressings in the box or cupboard a