第5页 IMPLEMENTING ARRANGEMENT NUMBER 5 ACCEPTANCE TESTING OF AN ADVANCED OPERATIONAL AVIATION WEATHER SYSTEM (AOAWS) TO THE AGREEMENT BETWEEN THE TAIPEI ECONOMIC AND CULTURAL REPRESENTATIVE OFFICE IN THE UNITED STATES AND THE AMERICAN INSTITUTE IN TAIWAN FOR

[接上页]

  The AOAWS project managment tasks for thisfiscla year include t-he following subtasks:
  
  .Developing, coordinating, and managing the work performed byUCAR, AIT's designated representative, and III.
  
  .Responding to information requests made by the Caa, TECRO's d-esignated representative.
  
  .Intgerfacing with project participants including the CAA, TER-RO's designated representative, CWB, CAA's cooperative partner, and airline.
  
  .Prepaaring progress reports and warranty activity reports.
  
  .Participating in AOAWS project-related meetings.
  
  .Preparing and submitting deliverable documents.
  
  .Preparing and submitting deliverable documents.
  
  .Preparing and submitting project-related correspondence.
  
  .Upating the AOAWS System Exstension Plan, when necessary.
  
  .Administering the AOAWS contract.
  
  Deliverables:
  
  Progress Report - First Report 19 April 2002Progress Report - Second Report 19 July 2002Warranty Activity Report - First Report11 October 2002Warranty Activity Report - Second Report 6 December 2002Resources Required:
  
  Staff:
  
  UCAR Administrative Assistance (0.25 FTE)US $ 22,050UCAR Project management (0.2 FTE)US $ 44,100III Project Management (0.5 FTE) US $ 52,500Travel:
  
  project Planning Meetings at CAA
  
  2 trips for 1 person at 1-week eachUS $ 15,600Purchase ServicesUS $ 11,825Task Total US $146,075----------------------------------------------------------------3.0 Monthly Schedule
  
  See attached FY2001 Task Schedule (Gantt Chart)
  
  4.0 Budget Summary
  
  System implementation, Testing, & maintenanceUS $154,425
  
  MM5 System Evaluation, Testing, & Maintenance
  
  (Part A) US $239,500AOAWS Project Management US $146,075────────────────────────────────
  
  LA#5 Subtotal (Master plan)US $540,000Additional Costs:
  
  MM5 Parallelization (Augmentation Plan)US $ 75,000MDS System Hardware for CKS Terminal 2 US $ 15,000────────────────────────────────
  
  LA #5 Grand TotalUS $630,000