第12页 1974年国际海上人命安全公约1989年修正案(附英文)

[接上页]

  Administration, thereby impaired."
  
  Regulation 15 Openings in watertight bulkheads in passenger ships
  
  The existing text of this regulation is replaced by the following:
  
  "Openings in watertight bulkheads in passenger ships (This regulation
  
  applies to ships constructed on or after 1 February 1992)
  
  1 The number of openings in watertight bulkheads shall be reduced to
  
  the minimum compatible with the design and proper working of the ship;
  
  satisfactory means shall be provided for closing these openings.
  
  2.1 Where pipes, scuppers, electric cables, etc., are carried through
  
  watertight subdivision bulkheads, arrangements shall be made to ensure the
  
  watertight integrity of the bulkheads.
  
  2.2 Valves not forming part of a piping system shall not be permitted
  
  in watertight subdivision bulkheads.
  
  2.3 Lead or other heat sensitive materials shall not be used in
  
  systems which penetrate watertight subdivision bulkheads, where
  
  deterioration of such systems in the event of fire would impair the
  
  watertight integrity of the bulkheads.
  
  3.1 No doors, manholes, or access openings are permitted:
  
  .1 in the collision bulkhead below the margin line;
  
  .2 in watertight transverse bulkheads dividing a cargo space from
  
  an adjoining cargo space or from a permanent or reserve bunker, except as
  
  provided in paragraph 10.1 and in regulation 16.
  
  3.2 Except as provided in paragraph 3.3, the collision bulkhead may be
  
  pierced below the margin line by not more than one pipe for dealing withfluid in the forepeak tank, provided that the pipe is fitted with a
  
  screwdown valve capable of being operated from above the bulkhead. The
  
  Administration may, however, authorize the fitting of this valve on the
  
  after side of the collision bulkhead provided that the valve is readily
  
  accessible under all service conditions and the space in which it is
  
  located is not a cargo space.
  
  3.3 If the forepeak is divided to hold two different kinds of liquids
  
  the Administration may allow the collision bulkhead to be pierced below
  
  the margin line by two pipes, each of which is fitted as required by
  
  paragraph 3.2, provided the Administration is satisfied that there is nopractical alternative to the fitting of such a second pipe and that,
  
  having regard to the additional subdivision provided in the forepeak, the
  
  safety of the ship is maintained.
  
  4.1 Watertight doors fitted in bulkheads between permanent and reserve
  
  bunkers shall always be accessible, except as provided in paragraph 9.4
  
  for between-deck bunker doors.
  
  4.2 Satisfactory arrangements shall be made by means of screens or
  
  otherwise to prevent the coal from interfering with the closing of
  
  watertight bunker doors.
  
  5 Subject to paragraph 11, not more than one door, apart from the
  
  doors to bunkers and shaft tunnels, may be fitted in each main transverse
  
  bulkhead within spaces containing the main and auxiliary propulsion
  
  machinery including boilers serving the needs of propulsion and all
  
  permanent bunkers. Where two or more shafts are fitted, the tunnels shall
  
  be connected by an intercommunicating passage. There shall be only one
  
  door between the machinery space and the tunnel spaces where two shafts
  
  are fitted and only two doors where there are more than two shafts. All
  
  these doors shall be of the sliding type and shall be so located as to
  
  have their sills as high as practicable. The hand gear for operating these
  
  doors from above the bulkhead deck shall be situated outside the spaces
  
  containing the machinery.
  
  6.1 Watertight doors, except as provided in paragraph 10.1 or
  
  Regulation 16, shall be power-operated sliding doors complying with the
  
  requirements of paragraph 7 capable of being closed simultaneously from
  
  the central operating console at the navigating bridge in not more than 60
  
  seconds with the ship in the upright position.
  
  6.2 The means of operation whether by power or by hand of any
  
  power-operated sliding watertight door shall be capable of closing the
  
  door with the ship listed to 15° either way. Consideration shall also be
  
  given to the forces which may act on either side of the door as may be
  
  experienced when water is flowing through the opening applying a static
  
  head equivalent to a water height of at least 1 m above the sill on the
  
  centreline of the door.
  
  6.3 Watertight door controls, including hydraulic piping and electric
  
  cables, shall be kept as close as practicable to the bulkhead in which the
  
  doors are fitted, in order to minimize the likelihood of them being
  
  involved in any damage which the ship may sustain. The positioning of
  
  watertight doors and their controls shall be such that if the ship
  
  sustains damage within one fifth of the breadth of the ship, as defined in
  
  Regulation 2, such distance being measured at right angles to the
  
  centreline at the level of the deepest subdivision load line, the
  
  operation of the watertight doors clear of the damaged portion of the ship
  
  is not impaired.
  
  6.4 All power-operated sliding watertight doors shall be provided with
此法规有错误,我来纠正。请点击在此 提交错误内容或者您纠正的内容!